The Lexington Visitors’ Center project includes the construction of a new 6,693 GSF building in place of the existing facility in Lexington, MA. The proposed program includes exhibit areas, offices, restrooms, and corridors.
The project uses all-electric systems. A gas-fired duct heater is provided as back up in case of an extended power loss.
Is the project achieving or targeting net zero energy?
Targeting
Is the project Net Zero or Net Zero Ready?
Net Zero Ready
Project Size in GSF
6.7K
Category of height
Low-Rise
How is the building all-electric for heating?
Air-source Heat Pump
Is the service hot water all-electric?
Yes
On-site renewable energy
0%
Is the owner purchasing off-site renewable energy to offset all electricity consumption?
No
The construction cost difference from "conventional" to being net zero "ready" (including incentives) for this building is
>-1% to 1%
Site EUI
32.1 kBtu/sf/year
Net Site EUI
0.0 kBtu/sf/year
What is the climate zone for this project?
5A Cool Humid