Project
University of Massachusetts Medical School, New Education and Research Building
Laboratory / Tech / Science
Worcester , MA | 2023
- 335K GSF
- 2 Companies
- 4 Professionals
About
Is the project achieving or targeting net zero energy?
Targeting
Is the project Net Zero or Net Zero Ready?
Net Zero Ready
Project Size in GSF
335K
Category of height
Mid-Rise
How is the building all-electric for heating?
Ground-source Heat Pump
Is the service hot water all-electric?
No
On-site renewable energy
0%
Is the owner purchasing off-site renewable energy to offset all electricity consumption?
No
The construction cost difference from "conventional" to being net zero "ready" (including incentives) for this building is
>-1% to 1%
Certifications related to Energy / Carbon
LEED, LEED ZERO
Site EUI
132.0 kBtu/sf/year
Net Site EUI
132.0 kBtu/sf/year
The EUI is
Modeled
What is the climate zone for this project?
5A Cool Humid